Stratford SS2122 Slurry Seal Works Planned Start and End Dates

Stratford SS2122 Slurry Seal Works Planned Start and End Dates

Slurry Seal footway treatment works are planned for this April and May in Stratford.  The 3 sites and their current start and end dates of the works are below.  The Prep work starting on the 26/04/21 and the Slurry Seal Treatment being completed around 13/04/21. However, these dates are liable to change due to a variety of reasons, weather being the primary one.

Road

Location

Prep Start

Prep Finish

DP Start

DP Finish

SS Start

SS Finish

Pedestrian Marshall

Duration

Traffic Management

 

 

 

 

 

 

 

 

 

 

 

St Gregorys Rd

Stratford

26-Apr-21

28-Apr-21

29-Apr-21

03-May-21

10-May-21

13-May-21

 

 

 

Warwick Rd - Gyratory

Stratford

26-Apr-21

28-Apr-21

29-Apr-21

03-May-21

10-May-21

13-May-21

2

1

Shuttle

Bridgeway - Gyratory

Stratford

26-Apr-21

28-Apr-21

29-Apr-21

03-May-21

10-May-21

13-May-21

4

2

Shuttle

 

A copy of the PR letter that would usually be sent out to the public but are unable to post due to issues related to Covid, can be found here.