Stratford SS2122 Slurry Seal Works Planned Start and End Dates
Stratford SS2122 Slurry Seal Works Planned Start and End Dates
Stratford SS2122 Slurry Seal Works Planned Start and End Dates
Slurry Seal footway treatment works are planned for this April and May in Stratford. The 3 sites and their current start and end dates of the works are below. The Prep work starting on the 26/04/21 and the Slurry Seal Treatment being completed around 13/04/21. However, these dates are liable to change due to a variety of reasons, weather being the primary one.
Road | Location | Prep Start | Prep Finish | DP Start | DP Finish | SS Start | SS Finish | Pedestrian Marshall | Duration | Traffic Management |
| | | | | | | | | | |
St Gregorys Rd | Stratford | 26-Apr-21 | 28-Apr-21 | 29-Apr-21 | 03-May-21 | 10-May-21 | 13-May-21 | | | |
Warwick Rd - Gyratory | Stratford | 26-Apr-21 | 28-Apr-21 | 29-Apr-21 | 03-May-21 | 10-May-21 | 13-May-21 | 2 | 1 | Shuttle |
Bridgeway - Gyratory | Stratford | 26-Apr-21 | 28-Apr-21 | 29-Apr-21 | 03-May-21 | 10-May-21 | 13-May-21 | 4 | 2 | Shuttle |
A copy of the PR letter that would usually be sent out to the public but are unable to post due to issues related to Covid, can be found here.